Default Process and time for the installation of the fast charger?

I understand from poking around this forum that Best Buy's Geek Squad comes to my house for $99 to check out the place then my data gets forwarded around until at some point wires are connected and I'm done.
Are the basic steps?
  • I buy car and drive home
  • I call Best Buy
  • They come by and do their thing
  • An electicrian calls me
  • Electrician does his work
  • I'm happy
This feels like a process I'll be enjoying a good while, especially with the holiday season. But approx how long should I be expecting?
wplate is offline   Reply With Quote
Sponsored Links
Advertisement
 
Old 11-22-2012, 04:37 PM   #2 (permalink)
Senior Member
 
JeffAnd's Avatar
 
Join Date: Apr 2012
Location: Wisconsin
Posts: 142
Garage
Default

The time it takes is the range of 2 to 3 weeks once Best Buy does the site visit.
Here is a detailed list of sequence.

1) You contact Best Buy geek squad to schedule a site assessment.
2) Best Buy does the site assessment.
3) Best Buy sends the site assessment report to Mr. Electric.
4) Mr. Electric send the site assessment report to a local electrican they are contracted to work with.
5) The local electrician contacts you with the estimated cost of the installation.
6) You then give the OK to install the system.
7) The local electrician then orders the Ford charging station from Mr. Electric.
8) The charging station is then drop shipped from Leviton distribution center to your local electrician.
9) Once receiving the charging station the electrician now can install it.
10) You pay the bill, and you are both happy.

Cost differences are due to distance the wires have to be run, and local electrical permit cost.

The cheapest installation is when the charger is located only a few feet from the circuit breaker panel.
The most expensive installation would be an unattached garage that is some distance away from the circuit breaker panel in the house.
JeffAnd is offline   Reply With Quote
Old 11-23-2012, 12:42 AM   #3 (permalink)
Junior Member
 
Join Date: Nov 2012
Posts: 3
Default

Thank you very much for the detailed reply. If I go this route I'll reply with the results.
wplate is offline   Reply With Quote
Reply

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
How fast is Level 2 charging? JeffAnd Ford Focus Electric Owners Forum 1 07-30-2012 06:18 PM
Best buy installation of the Ford Charging station JeffAnd Ford Focus Electric Owners Forum 8 05-15-2012 04:43 PM
6.6kw charger installation requirements? voip-ninja Main Ford Focus Forum 11 08-31-2011 11:16 AM
Fast Company - I-5 Will Be The Electric Interstate Charged Up Other/Competitor Forum 1 07-19-2011 09:23 AM
Time - Will Israel's Electric Cars Change the World? Charged Up Main Ford Focus Forum 2 04-28-2011 08:58 AM

Powered by vBadvanced CMPS v3.2.3

All times are GMT -4. The time now is 03:12 AM.


Powered by vBulletin® Copyright ©2000 - 2022, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO 3.6.0 PL2
Garage Plus vBulletin Plugins by Drive Thru Online, Inc.
vBulletin Security provided by vBSecurity v2.2.2 (Pro) - vBulletin Mods & Addons Copyright © 2022 DragonByte Technologies Ltd.